1
|
- Period of concession is 70 years.
- Project with clear mandate and milestones.
- Minimum 60% IT space
- First milestone of 4 lakh sft. of IT space to be achieved within 24
months.
- In principle approval of SEZ obtained.
|
2
|
- IDCO
- Location: next to existing Fortune Tower, C.S.pur, Bhubaneswar
- Signature Building over 5.47 acres .
- A state-of-the-art high rise building (18 storied).
- Project Cost : Rs. 146 Cr.
- 15 Firms have been short listed after pre-qualification
- BDA has been requested to allow “commercial land use” with FAR of 2.00
& allow for relaxation in Building height.
|
3
|
- I.T. Deptt.
- Estimated cost – Rs.35.67 Crore.
- Land Area : 251.55 acres (101.80 Ha)
- Land Status : Government land under transfer to IDCO
- 10 Firms have submitted EOIs.
- Process for SEZ notification and next stage of bidding process to be
initiated after transfer of land.
|
4
|
- I.T. Deptt.
- Estimated cost – Rs.352.03 Crore.
- Land Area : 27.131 acres (10.98 Ha)
- Land currently with IDCOL. Under the process of being transferred to
IDCO
- Process for SEZ notification to be initiated after transfer of land
|
5
|
- IDCO
- Estimated cost – Rs. 76.06 Crore
- Objective to provide quality built-up space for IT/ITES, Corporate
offices, social infrastructure such as retail & shopping,
entertainment & leisure etc
- About 3.5 lakh sft of built-up space over 3.47 acres of land in Civil
Township
- Project to be developed in PPP format
- 5 Firms short-listed after open invitation
- RFP already issued to short-listed bidders for submission of technical
and financial bids. Last date for submission is 30.4.2007
- Final selection of the Developer on the basis of highest land premium
|
6
|
- 4 Firms have been short-listed after open invitation
- Lease of land sanctioned by the Collector, Ganjam.
- Land located in green belt zone. Application for change in land use
submitted.
- RFP to be issued after land related issues are sorted out.
|
7
|
- I.T. Deptt.
- Estimated cost - 35.67 Crore.
- Total Land – 82 Ha.
- IT majors like WIPRO, TCS, MindTree, Genpact have agreed to be Anchor
Tenant and Co-Developers.
- Project SPV to be formed after notification of SEZ.
|
8
|
- IDCO/ Industries Deptt.
- Estimated cost - 712.00 Crore.
- To be developed over 1093 Ha. land.
- In principle approval for SEZ obtained.
- Land details being worked out.
|
9
|
- S&T Deptt./IDCO
- Cost : 100 Cr.
- 63.299 acres land in Andharua earmarked fro this project.
- RFQ received on 07.05.2007, technical bid evaluated, financial bid will
be opened shortly.
|